Protective pipes made of resistant PE100-RC material with increased resistance to point loads and crack-initiating stress peaks. For underground installation of high and medium voltage lines with continuous service temperatures up to 40°C.
Solid wall pipe in black (optionally with red identification stripes or co-extruded, coloured outer layer) | Complete metre marking in accordance with standard specifications
EMDS protective conduit for buried installation for blowing in, pulling in and inserting cables and fibre optics | Cable protection conduit for high- and medium-voltage cables with continuous service temperatures up to 40°C
EMDS conduit pipe High performance class PE100-RC at Ausschreiben.de EMDS conduit pipe PE100-RC with protective jacket at Ausschreiben.de
This product is also available with ISCC Plus sustainability certification on request. We have summarised all the information for you here -> ISCC Plus
Accessories
Traverse for coil drums
The specialist for professional slinging of drums on forklifts and industrial trucks. More information
Rerounding clamps
The tackler for maximum rounding force when welding with electrofusion fittings/sockets. More information
When laying in a sand bed, the excavated material must be replaced with a sand bedding in accordance with DIN EN 805. Restrictions on the grain sizes of the bedding material must be observed.
Without sand bedding
Due to the verification by an independent testing institute, the installation is possible without a sand bed. This eliminates the additional expense of replacing the excavation with a sand bedding in accordance with DIN EN 805 (transport, landfill).
Ploughing
In the ploughing method, the soil is displaced by a plough blade and the pipeline is placed on the bottom of the soil.
Milling
In the milling process, a pipe trench is cut into the subsoil by machine and the pipeline is laid on the bottom of the trench.
Pipe bursting
Static pipe bursting is the renewal of the old pipeline along the same of the old pipe route, which is shattered by the bursting head and the remaining fragments are pressed into the surrounding soil.
Horizontal Directional Drilling (HDD)
The new installation by HDD is usually carried out in three successive work steps. With the continuous pilot borehole, which is controlled by positioning the route is determined. This is followed by the widening of the borehole and the pulling in of the pipe string.
Relining
In the case of relining with annular space, the new pipe string with a smaller cross-section is pulled into the cleaned old pipeline using a pull-in device.
Soil Displacement Method
In the soil displacement method, a pneumatically operated displacement hammer, a so-called "rocket", is used to excavate an underground cavity. The new pipeline is then pulled into it.
Similar products
LHT® E-POWER
Protective pipes for underground cabling of high and extra-high voltage lines up to 525 kV. More information
EMDS PE100
Protective pipes with secured static characteristic values and internal pressure resistance. More information
Want to find out more? We look forward to hearing from you.
This website uses cookies. Some of them are necessary, while others help us to improve this website and your experience. I agree and can revoke or change my consent at any time with effect for the future.